Work Plan
Schedule Start Date of March 17, 2003
CGI Group (formerly American Management Systems) was selected as the winning proposal for the ORCA RFP 2002-0600-3464 on October 15, 2002. Contract negotiations, federal approval and the final state approval of the contractual arrangement occurred from November 2002 through February of 2003. The final approval and signing of the contract occurred the week of March 10, 2003. Implementation and on-going maintenance has occurred as outlined in the following table of ORCA project milestones:
| Date/Time | Milestone |
| March 17, 2003 | AMS arrives on site in Juneau. |
April 1, 2003 |
OCS ORCA Project Team all reassigned to Juneau for 18-month project duration. |
April 2, 2002 |
AMS/OCS Project Kickoff meeting. |
Week of April 7, 2003 |
Initial high level design sessions begin in Juneau. |
Week of April 14, 2003 |
Preliminary performance test of ORCA application in Bethel |
April 7 - June 15, 2003 |
Initial Design Sessions continue in Juneau |
May 2004 |
Pilot System Test |
July 2004 |
Statewide Rollout/Implementation |
February 2005 |
Financial Management Rollout/Implementation |
June 2005 |
System Warranty and Maintenance |
|
|
|
ORCA System Upgrade Release Schedule |
September 2004 |
Version 1.2 |
November 2004 |
Version 1.3 |
February 2005 |
Version 1.4 |
March 2005 |
Version 1.5 |
May 2005 |
Version 1.6 |
June 2005 |
Version 1.7 |
September 2005 |
Version 1.8 |
December 2005 |
Version 1.9 |
April 2006 |
Version 2.0 |
June 2006 |
Version 2.1 |
December 2006 |
Version 2.3 |